Extremely limited migration window
The entire relocation had to be completed within one weekend.
Case study
End-to-End Physical Migration with Zero Damage and Fast Recovery
A global financial technology company needed to relocate its entire IDC from a commercial data center to a new in-house server room within a single weekend.
ESUN provided full physical-layer migration services, covering shutdown coordination, labeling, disassembly, packing, transportation, rack installation, cable reconstruction, and onsite support during system verification.
The entire relocation had to be completed within one weekend.
Servers, storage, and network devices required precise handling and controlled transportation.
Both the old and new locations had strict entry, exit, and registration requirements.
The customer expected systems to be ready for verification as soon as power was restored.
Conducted site walkthroughs, verified rack positions, pathways, elevator limits, device lists, and created an hour-by-hour migration plan.
Worked with the customer IT team to label devices and cables, document connections, and safely disassemble equipment.
Used anti-static materials, shock-proof protection, and lift-gate vehicle transport with controlled loading and unloading.
Completed rack positioning, device mounting, power connection, structured cabling, and onsite coordination for power-on checks and system verification.